Procurement Timeline for a 1 MW Commercial Solar Project: From RFQ to Delivery

Buying equipment for a megawatt-scale solar project follows a predictable sequence. Here is an outline of the steps, decision points and what to have ready at each.
In this article
How do you procure equipment for a 1 MW solar project?
Work through a sequence: define the design and specs, issue an RFQ, shortlist and verify suppliers, test samples, negotiate and sign the contract, pay in stages, inspect before shipment, ship and clear customs, and accept the goods on site. Doing the early steps carefully usually saves more time than rushing to the order.
The sequence
1. Define the design and specs
Fix module power class and technology, inverter type and size, racking, interconnection, and the balance of system. See module technology, inverters, racking and the BOS checklist.
2. Issue the RFQ
State specs, quantity, Incoterm, delivery date, documents required and quote deadline. See how to write an RFQ and use the RFQ form.
3. Compare quotes on a landed basis
Convert currencies, add freight, duties and fees, and compare price per watt. See comparing prices and currency risk.
4. Verify the shortlist
Check company details, references, documents and take a factory tour. See verifying a supplier.
5. Order a sample
Check the product against the datasheet. See ordering samples.
6. Negotiate and sign the agreement
Agree specs, delivery, acceptance, warranty and remedies. See key clauses.
7. Pay in stages
Deposit, milestone and balance tied to evidence. See deposit and balance.
8. Inspect before shipment
Independent pre-shipment check before you release the balance. See pre-shipment inspection.
9. Ship, clear customs and deliver
Plan transport, insurance and import clearance. See freight and importing into Canada.
10. Accept on site
Check counts, damage and documents, and run the agreed acceptance tests. Keep records for warranty claims. See handling claims.
Approximate durations
Durations depend on the supplier, season and market, so ask for written schedules. As a planning aid, treat design and RFQ as weeks, supplier verification and samples as weeks, production and shipping as the longest block, and customs and delivery as days to weeks. Order long-lead items first. See planning around lead times.
Where TradYard fits
Use B2B listings and the shop for specs and prices, supplier profiles and live tours for verification, an RFQ for quotes, and the Deal Room for agreements and staged payments.
Frequently Asked Questions
How many suppliers should I quote?
Three to five qualified suppliers is a common range.
When should I order the inverters?
As soon as the design is fixed, if their lead time is long compared with the modules.
Can I split the order across suppliers?
Yes, but check compatibility and take responsibility for integration.
Do I need an independent inspection?
For a project of this size, it is a sensible precaution.
What documents do I keep?
Contract, datasheets, certificates, test and inspection reports, shipping documents and acceptance records.
Written by
Amir Oboudi
October 11, 2026
Related Articles
View all
How to Sell Energy Equipment on TradYard: A Supplier's Guide to Listings, Documents and Deals
Factories, distributors and surplus sellers can reach buyers on TradYard. Here is how to apply, build a listing buyers trust, host a live factory tour and handle quotes and deals.

How Surplus and Used Energy Equipment Auctions Work: A Buyer's Guide
Auctions can put surplus and used energy equipment in reach at a lower price, but only if you read the lot, set a limit and plan freight. Here is the process, step by step.

Backup Power for Commercial Sites: Generators, UPS and Batteries Compared
Generators, UPS units and batteries solve different parts of the backup problem. Here is how they compare and how to combine them for a commercial site.
Stay in the Loop
Get weekly market insights, auction alerts, and expert tips delivered to your inbox.
Unsubscribe anytime. No spam.